Complementary Technology
 
Home

Papers_and_Presentations

Leak Detection and Ultrasonics

Partial Discharge

Case Study : Use of Complimentary Technology

In another station, a 500 MW unit, with step up transformers of the 20 kV to 400kV range, (single phase OFWF) type were subjected to high electrical stresses due to failure of current transformers in the substation and were suspect. The anxiety of station management further increased when one of the transformers failed. The remaining transformers were surveyed for a condition determination to ascertain their reliability.

The survey using acoustic fault detection indicated ultrasonic activity at many places. The correlation with DGA indicated no abnormality. It was recommended to continue monitoring the locations for any increase in the magnitude of activity. Any increase was expected to result in increased evolution of gases along with the deterioration of the oil, which would be reflected in the DGA results at that time. In the same transformer vibration measurements and spectra were taken at all the corners. At one of the corners near the On-Load Tap Changer (OLTC), high overall vibration levels (5.57 mm/sec and 7.11 mm/sec ) were observed. Also in the spectra, 6X peaks were dominant compared to 2X peaks which are normal. (X=50 Hz.) These 6X levels indicated an intermediate level of severity. It was recommended to investigate further and inspect for any physical damage. It was also intended to verify the exact positions of jack (coil holding to wall) so that vibration measurement points could be located near it in future surveys.

During the next inspection, the plant engineers noted the loose nuts at the jack. The tightening of the nuts restored the core to the original condition and the overall vibration levels reduced to minor levels. This confirmed the looseness of coil, which was vibrating during operation. This kind of looseness damages the coil over a period (slow damage progression) and also damages the insulation. When the failure occurs it is always catastrophic requiring total rebuild of the transformer. This kind of failure, if experienced, would cost the utility generation loss of more than 25 days (about 171 million kWh). The cost of repair and transportation to & from the manufacturer’s works would be additional (about Rs15 million, $341K US Dollars).

 
 
Home Page | Transformer Vibration | SPdM Course | Leak Detect & UT | Fault Detector | Products